Update on 35th Avenue SE Reconstruction

Update on 35th Avenue SE Reconstruction ~ March 1
Posted on 03/01/2019
An image of the road construction on 35th Avenue SE in Mill CreekConstruction on 35th Avenue SE through Mill Creek ceased in early February due to snow/ice and freezing temperatures. However, work is again underway. Concrete work is in process with the goal of wrapping up at the end of this week.

The asphalt work is the last major hurdle. To lay asphalt, the ground temperature needs to be at least 35 degrees. In cold weather, the ground temperature can be up to 8 degrees cooler than air temperature. Following asphalt application, permanent road marking will be completed. As long as ground temperature cooperates, the City’s goal is to reopen the road by March 15. The City is doing everything it can to drive toward that date.

The City is excited to be in this final stretch! Thank you for your patience throughout this lengthy project!

For more information, visit www.cityofmillcreek.com/35th.